धारा 71 · Permit-to-work on electrical equipment
अक्षर आकार — स्तर 1, कुल 4 में से
(1)
If work is to be carried out adjacent to the electrical equipment or any other part thereof by other than the competent metro rail employee, such work shall be done only when and for such time as the person-in-charge of the work has obtained a permit-to-work, from a metro railway employee authorised for the purpose by special instructions which shall lay down the detailed procedure of obtaining, granting and cancelling of the permit to work, ensuring utmost safety.(2)
The metro rail employee authorised under sub-rule (1) shall grant such permit to work only with the approval of Traction Power Controller.(3)
A permit to work under sub-rule (1) shall be obtained if work is to be carried out or any worker is required to come within 2 metres (6'-7') of the overhead equipment.(4)
The permit to work shall be issued by any competent traction distribution official not lower in rank than a senior Lineman pertaining to the section concerned, subject to prior sanction of Controller (Traction Distribution).इस धारा पर आपका निजी नोट