MMCNPIT Act 193Chapter XII · Control Over Buildings
Section 193 · Completion certificate, permission to occupy or use
Text size — level 1 of 4
(1)
Every person constructing a building shall, within one month after the completion of construction of such building, deliver or send or cause to be delivered or sent to the Chief Officer at his office, notice in writing of such completion and shall give to the Chief Officer all necessary facilities for inspection of such building:Provided that, -(a)
such inspection shall be commenced within seven days from the date of receipt of the notice of completion; and(b)
the Chief Officer may, not later than one month from the date of receipt of the notice of completion, by written intimation addressed to the person from whom the notice of completion was received, -(2)
No person shall occupy or permit to be occupied or use or permit to be used any such building constructed or part thereof affected by such construction, until, -(a)
the permission referred to in proviso (b) to sub-section (1) has been received, or(b)
the Chief Officer has failed for one month after the receipt of the notice of completion to intimate as aforesaid his refusal of the said permission.(3)
Whoever-(a)
occupies or permits to be occupied any such building or part thereof affected by such construction without giving any notice as required under subsection (1) or in contravention of the provisions of sub-section (2); or(b)
fails to comply with any order or requisition made under sub-section (1),The offence at a glance
- Fine
- ₹5,000
- Cognizable
- Non-cognizable
- Bailable
- Bailable
- Triable by
- Any Magistrate
- Non-cognizable — Police cannot investigate without a Magistrate's order
- Bailable — Bail is your right — it can be granted at the police station
Derived from the First Schedule Part II rule — not listed section by section