ODMRPCP Rules 40Chapter X · Design and Inspection of Equipment for Electric Traction
Section 40 · Approval of energization of high tension lines
Text size — level 1 of 4
(1)
Application shall be submitted at least a fortnight before energization of high tension lines to the Electrical Inspector of the Government for Delhi Metro Rail Corporation for the following, namely-(a)
formal approval, if not already received to the design and layout of all high voltage equipment including traction sub-stations, transmission lines, 25 kV/33 kV and 1500 V DC feeders, switching stations, booster stations, etc.;(b)
approval for energization of high tension installations mentioned above including overhead equipment for AC/DC traction ;(c)
the application should be accompanied by documents as specified in AC/DC Traction Manual.(2)
On receipt of an application under sub-rule (1), the Electrical Inspector shall scrutinize and inspect the design and installations in respect of the following, namely-(a)
the layout and design for receiving sub-stations, traction sub-stations auxiliary sub-stations, 1500 V DC/25 kV AC overhead equipment and other installations for compliance with the Indian Electricity Act, 1910 (9 of 1910) and the rules made thereunder and the relevant Indian standards or International standards; and(b)
inspection of completed installations, either personally or by deputing his officers for compliance with the safety requirements.(3)
After conducting the inspection under sub-rule (2), the Electrical Inspector shall convey his approval for the energization of 25 kV/33 kV/1500 V DC feeder lines from receiving sub-stations, energization of receiving sub-stations, traction sub-stations, auxiliary sub-stations, traction sub-stations to feeding posts, switching stations, booster transformer stations, track cabins and auxiliary transformer stations subject to such conditions as he may consider necessary.Your private note on this section