ODMRPCP Rules 4Chapter II · Preparation for Opening of the Metro Railway
Section 4 · Supply of documents to the Commissioner
Text size — level 1 of 4
(1)
The Chief Executive Officer shall, while making reference to the Commissioner for inspection and report on the safety of the metro railway under sub-rule (2) of Rule 3, furnish all relevant document, to the Commissioner from the following list of documents, namely-(a)
Tabulated details;(b)
Index plan and sections ;(c)
Drawings of works ;(d)
Certificate ;(e)
List of infringements of moving and fixed dimensions ;(f)
Working orders to be enforced at the operations control centre and at each station ; and(g)
Administrative note giving salient features of the project.(2)
The documents referred to in sub-rule (1) shall indicate the distances from the same fixed point in kilometres and decimals up to two digits and the fixed point shall be clearly defined in a note on the plan and section sheets of the work documents.(3)
The datum adopted shall be mean sea level as fixed by the Survey of India and heights shall be mentioned with reference to the datum in metres and decimals up to two digits.(4)
The documents referred to in sub-rule (1) shall be signed by atleast an officer equivalent to senior administrative grade rank except the certificate which shall be singed by the Chief Executive Officer himself.(5)
The Chief Executive Officer shall furnish such documents to the Commissioner, as far as possible, at least one month in advance of the stipulated date of inspection.Your private note on this section