FCAW Rules 5
धारा 5 · Revised Administration Approval
अक्षर आकार — स्तर 1, कुल 4 में से
(1)
If the detailed estimate of any project whom prepared exceeds the amount administratively approved by ten per cent or if it becomes apparent during the execution of any work that the amount administratively approved will be exceeded by ten per cent owing to the increase of rates or other reasons, the revised administrative approval of the competent authority to the increased expenditure shall be obtained without delay. Similarly, revised administrative approval shall be obtained to important modifications of the proposal originally approved even though the cost thereof may be covered by savings on other items.(2)
Administrative approval shall require renewal if funds have not been appropriated to the work or scheme in question in either of the two budgets succeeding the date of original approval.Example - An Administrative approval given to a work in the year, 1971-72 ceases to be operative on 31st March, 1972 and requires renewal unless the work finds a place in the budget passed for 1972-73 or 1973-74, or had funds appropriated to it by an additional grant in 1972-73.इस धारा पर आपका निजी नोट
यह नोट सिर्फ़ आप देख सकते हैं।