FCAW Rules 12
धारा 12 · Fees to Staff
अक्षर आकार — स्तर 1, कुल 4 में से
- Except the Electrical Engineer for whose services the scale of fee payable was notified, vide Notification No. 820-6-14126, dated the 6th November, 1924, the Administration shall pay to the Government on account of services rendered by the officers of the Public Works Department, the fees detailed in the table, namely :-Table
| Description of work | If the estimated cost of the work is less than Rs.10,000 | If the estimated cost of the work is from Rs.10,000 to Rs. 29,999 | If the estimated costs of work is Rs. 30,000 orover |
| 1 | 2 | 3 | 4 |
| For visiting a site and giving advice preparatory to design | Travelling allowance according to Government rules plus a feeof Rs. 50, for each day or part of a day | ||
| For the preparation of preliminary plans and estimates bycubic measurement of otherwise | 1¼ per cent of the estimated cost | 1 per cent of the estimated cost | ¾ per cent of the estimated cost |
| For the preparation of general drawing plans (Estimates),elevations, sections and specifications | 1¼ per cent of the estimated cost | 1 per cent of the estimated cost | ¾ per cent of the estimated cost |
| For the preparation of half inch, full size and otherdetailed drawings | Ditto | Ditto | Ditto |
| For the interviews and correspondence with the Engineer Incharge of Construction to an extent not amounting to supervision | Ditto | Ditto | Ditto |
| For the supervision of construction including periodicalinspection to the extent necessary to ensure efficientconstruction and the issue of all necessary orders regarding thework and the tendering of the advice during execution | 3 per cent of the estimated cost | 3 per cent of the estimated cost | 2 per cent of the estimated cost |
| For the preparation of plans and estimates and constructionthrough the staff of the Public Works Department | 7 per cent Departmental Charges | ||
| For the preparation of plan of the town where none alreadyexists, and such preparation is an essential preliminary to thepreparation of the plans and estimates for the work underconsideration | Such sum as may be agreed upon in each case before thepreparation of the plan is in hand |