DMRG Rules 18Chapter III · Signals and Control
Section 18 · Working of signals and points
Text size — level 1 of 4
(1)
Control of signals and points will be from a route setting panel. Complete routes, points and signals, will be cleared by a signal operation under normal conditions.(2)
Any failure of vital equipments shall cause the signalling system to display a more restrictive indication.(3)
Any route which has been cleared for a train shall not be cancelled until it is cleared by the train entering the route except,-(a)
in case of emergency ; and(b)
in case where operating conditions require that an alternate route be cleared. In this case the alternative route shall not be made available for clearance until the pre-set time has elapsed from the time the original route was blocked.(4)
In conditions of failure of route setting controls, points can be set individually from Operations Control Centre, Station Control Room or locally as may be necessary.Your private note on this section