The Central India Spinning, Weaving and Manufacturing Company Limited, The Empress Mills, Nagpur (Acquisition and Transfer of Undertaking) Act, 1986 17अध्याय VI · Commissioner of Payments
धारा 17 · Claims to be made to Commissioner
अक्षर आकार — स्तर 1, कुल 4 में से
- Every person having a claim other than the claim relating to gratuity or compensation for retrenchment or closure against the proprietors with regard to any of the matters specified in the Schedule pertaining to the undertaking, shall prefer such claim before the Commissioner within thirty days from the specified date:Provided that, if the Commissioner is satisfied that the claimant was prevented by sufficient cause from preferring the claim within the said period of thirty days, he may entertain the claim within a further period of thirty days but not thereafter.