JSERC Regulations 3
धारा 3 · Recovery of Charges
अक्षर आकार — स्तर 1, कुल 4 में से
- 3.1 The Distribution Licensee shall be authorized to recover charges for the supply of electricity from any person requiring such supply in accordance with the provisions of the Act and these Regulations and such charges shall include:(a)Recovery of such expenses as may be reasonably incurred by the Distribution Licensee in providing electric line or electrical plant used for giving such supply in accordance with these Regulations;(b)Charges for electricity supplied by licensee in accordance with the tariff order issued by the Commission;(c)Any other charges as may be approved by the Commission from time to time.3.2.3Where the provision of supply to an applicant entails works, not being works referred to in clause 3.2.1 and 3.2.2 above of these Regulations, for augmentation/upgradation of the distribution system, the Distribution Licensee shall be authorized to recover from the applicant such portion of the expenses reasonably incurred on such works as the load or additional load applied for bears to the incremental capacity that will be created by augmentation of the distribution system as per the schedule of charges approved by the Commission from time to time. Provided that where the load or additional load applied for by the applicant does not exceed one third of the capacity that will be created by augmentation of the distribution system, the Distribution Licensee shall not be entitled to recover any expenses under this clause 3.2.3 of these Regulations form such applicant.3.2.4Where the Distribution Licensee permits the applicant to carry out works of laying service line and/or dedicated distribution facilities for the power supply requisitioned by him, the Distribution Licensee shall not be entitled to recover expenses relating to such portion of work so carried out by the applicant. Provided however that the Distribution Licensee shall be entitled to recover from the applicant, supervision charges as per schedule of charges approved by the Commission from time to time, not exceeding 15 percent of the labour cost that would have been incurred by licensee in carrying out such work.Provided further that the applicant shall have to get the works carried out by licensed electrical contactor as per the estimate and lay-out approved by the Distribution Licensee. The material purchased by the applicant in such cases should conform to relevant BIS specification or its equivalent and should bear its mark where applicable. The Distribution Licensee may ask for documentary evidence to verify the quality of material.3.2.5The service line and /or the dedicated distribution facility, not withstanding that it has been paid for by the consumer, shall remain the property of the Distribution Licensee who shall maintain it and who shall have the right to use the same for supply of electricity to any other person provide that such supply should not adversely affect the supply to the consumer who has paid for it. 3.3Charges for Electricity Supplied. - 3.3.1 The Distribution Licensee shall recover electricity charges for the electricity supplied to the consumer as per the tariff determined by the Commission from time to time in accordance with the provisions of Electricity Act 2003.Provided that in case of distribution of electricity in the same area by two or more Distribution Licensees, the Commission may fix only the maximum ceiling of tariff for retail sale of electricity.3.3.2Unless otherwise specified, all HT and LT charges refer to one point of supply and each separate establishment shall be given separate point of supply. 3.3.3The charges for electricity supplied may include fixed charges, energy charges, minimum charges and all other surcharges including fuel price adjustment surcharge, delayed payment surcharge as per tariff in force from time to time. 3.3.4The Distribution Licensee is also authorized to recover such surcharge and charges for wheeling as may be specified under provisions of Sub-Sections (2) and (3) of Section 42 of the Act and such additional surcharge as may be specified under provisions of Sub-Section(4) of Section 42 of the Act. 3.3.5In addition to the charges fixed by the Commission, the consumer shall also pay all taxes, duties and statutory charges as required under any law for the time being in force.
3.2
Cost of Service Connection/Extension/Upgradation. - 3.2.1 The Distribution Licensee shall be authorized to recover from the applicant all expenses reasonably incurred in laying the service line from the distribution mains to the point of supply based on the schedule of charges approved by the Commission from time to time.3.2.2
Where the provision of supply to an applicant requires works of installation of dedicated distribution facilities, the Distribution Licensee shall be authorized to recover all expenses reasonably incurred on such works from the applicant based on the schedule of charges approved by the from time to time.इस धारा पर आपका निजी नोट
यह नोट सिर्फ़ आप देख सकते हैं।