JKAR Act 8अध्याय III · Orders Authorising the Construction of Aerial Ropeways
धारा 8 · Cessation of powers given by an order
अक्षर आकार — स्तर 1, कुल 4 में से
- If a promoter authorised by an order to construct an aerial ropeway does not, within the time specified in the order,-
(a)
succeed in raising the full amount of capital required for the completion of the aerial ropeway ; or(b)
make, in the opinion of the Government, substantial progress with the construction of the aerial ropeways ; or(c)
complete the construction thereof, the powers given to the promoter by such order shall, unless the Government extends the time so specified, cease to be exercised.इस धारा पर आपका निजी नोट