धारा 41 · Foundations. Section 43(2), 57(2)(m)
अक्षर आकार — स्तर 1, कुल 4 में से
(1)
The foundations of every building shall be so constructed as to sustain the combined dead load of the building and the super-imposed load and to transmit those loads to the sub-soil in such a manner that the pressure on the sub-soil shall not exceed the safe pressure specified below:| S.No. | Type of rocks and Soil | Presumptive safebearing capacity | Remarks |
| (a) Rocks- | Kg/cm2 | ||
| 1. | Rocks (Hard) without lamination and defects for example,granite trap and diorite | 33 | .. |
| 2. | Laminated rocks, for example, stone and lime stone in soundcondition | 16.5 | .. |
| 3. | Residual deposits of shattered and broken bedrock and hardshale, cemented material | 9 | .. |
| 4. | Soft rock | 4.5 | .. |
| (b) Non-cohesive soils - | |||
| 5. | Gravel, sand and gravel, compact and offering high resistanceto penetration when excavated by tools. | 4.5 | See note 1. |
| 6. | Coarse sand, compact and dry | 4.5 | Dry mean that the ground water level is at a depth not lessthan the width of foundation below the base of the foundation. |
| 7. | Medium sand, compact and dry | 2.5 | .. |
| 8. | Fine sand, silt (dry lumps easily pulverised by the fingers) | 1.5 | .. |
| 9. | Loose gravel or sand gravel mixture; loose coarse to mediumsand dry. | 2.5 | See note 1. |
| 10. | Fine sand loose and dry | 1 | .. |
| (c) Cohesive soils - | |||
| 11. | Soft shale, hard or stiff clay in deep bed, dry | 4.5 | This ground is susceptible to long term consolidationsettlement. |
| 12. | Medium clay, readily indented with a thumb nail | 2.5 | .. |
| 13. | Moist clay and sand clay mixture which can be indented withstrong thumb pressure | 1.5 | .. |
| 14. | Soft clay, indented with moderate thumb pressure | 1 | .. |
| 15. | Very soft clay which can be penetrated several centimetreswith the thumb | 0.5 | .. |
| 16. | Black cotton soil or other shrinkable or expensive clay indry condition (50 per cent saturation) | .. | See note 2. To be determined after investigation. |
| (d) Peat - | |||
| 17. | Peat | .. | See notes 2 and 3 to be determined after investigation. |
| (e) Made up ground - | |||
| 18. | Fills or made up ground | .. | See notes 1 and 4. To be determined after investigation. |
(2)
The loads shall not cause such settlements of the building or any part of the building as may impair its stability.(3)
For building 3 storey high, foundation shall be designed after making standard tests or establishing the safe bearing pressure of the soil and the foundations shall be taken down to such a depth or so constructed as to render the building immune from damage, from upheaval and movement due to seasonal variations in the content of the moisture in the ground.इस धारा पर आपका निजी नोट