During regulation of power supply, through a hydro generating station, in order to avoid spillage of water, if a buyer cannot be found or is not found for the full quantum of power rendered surplus, the generating station can inject power under Unscheduled Inter-change (UI) mechanism, if grid conditions allow, with the permission of the Regional Load Despatch Centre in which it is located, subject to the stipulations in the Central Electricity Regulatory Commission, (Unscheduled Inter-change charges and related matters) Regulations, 2009, as amended from time to time. The loss of energy charge, in case of spillage of water, shall be made good from the revenue earned through sale of power and/or UI from injection of power rendered surplus due to regulation, on first charge, and the balance amount shall be adjusted in accordance with regulation 16.